How long does a new driveway take?

By Terry O'Reilly, owner, 17 years on the tools. Updated . 4 min read.

Most two-car driveways in Milton Keynes take two to three days. Block paving is 2 to 3 days, resin bound is 2 days plus usually about 48 hours to cure, and tarmac is 1 to 2 days. Terry gives you a day count with the written quote and aims to stick to it; what adds days is a big dig out, steps or walls, and heavy rain on a resin job.

Mini digger breaking out an old drive on day one, Milton Keynes area
Mini digger breaking out an old drive on day one

What happens on each day?

Day one: dig out and base. The old surface comes out, along with anything soft underneath. Edging goes in on concrete, drainage is laid where it is needed, then 200mm to 250mm of stone goes in and is compacted with a plate. This is the day nobody sees and the day that decides whether the drive is still flat in ten years.

Day two: lay. For block paving, a levelled sand bed and the blocks, cut in at the edges and around drains, then compacted and sanded. For resin bound, the resin and stone are mixed on site and trowelled by hand over the base. For tarmac, it is laid hot and rolled.

Day three, if needed. Cutting a complicated pattern, building steps or a wall, a path to the door, or finishing the sealing. Then the site is swept, the waste goes and you get the guarantee in writing. There is a fuller day-by-day account in what happens when we lay a block paving drive.

How long does each material take?

DrivewayOn sitePark on itWhat adds time
Block paving2 to 3 daysUsually the day after we finishCurves, patterns, steps, lots of cuts
Resin bound2 daysUsually about 48 hours after we finishReplacing a bad base first, rain
Tarmac1 to 2 daysUsually the day after we finishA very big area, new drainage

Swipe the table sideways to see all of it.

Patios vary more than drives because gardens vary more than fronts. A flat garden with a simple patio is 2 to 4 days; levelling and steps is 3 to 5 days, up to a week with a retaining wall. See patios.

What can slow a job down?

  • What is under the old drive. Old concrete takes longer to break out than old blocks. Tree roots and forgotten footings add hours. I check on the visit but I cannot see through concrete.
  • Drainage. If the house needs a soakaway or a channel drain that was not there before, that is part of day one.
  • Weather. Resin needs a dry surface. Block paving and tarmac carry on in most rain. Frost stops everything.
  • Extras. Steps, walls, a dropped kerb, a path round the side, lighting.
  • Deliveries. Materials are ordered for the start date. If a supplier lets us down, you hear about it the same day.

None of these change the price once it is agreed without talking to you first. Only the day count can move, and I tell you when it does.

Would you rather just ask Terry?

A photo and a question on WhatsApp gets a straight answer, usually the same day.

How much mess and noise should I expect?

Day one is the noisy one: a breaker on the old surface, a digger or a lot of shovelling, a skip or grab lorry, and a plate compactor. Day two is quieter, with a saw for the cuts. We sweep the site and bag the waste every day, so there is no mound of rubble on the front for a week.

You will need to park on the road for the days we are there and, for resin, two days after. On a terrace street in Wolverton that can mean a short walk, so tell the neighbours; most are glad to know when the skip is coming and going.

Does the size of the house change the day count?

Less than you would think. A two-car drive on a 1930s semi in Bletchley and a two-car drive on a newer detached house on the estates take about the same time, because the base work is the same. What changes it is shape and detail. A straight rectangle in one colour is quick. A curved drive with a border, a circle feature and steps to the door is a third day.

Long drives on the bigger plots around Woburn Sands take longer simply because there is more of everything, and that is when tarmac earns its place: a big area goes down in a day.

How soon can Terry start?

It depends on the time of year and what is already booked. I give you a start date with the quote. Spring and early summer are the busiest; autumn is a good time to get a drive done before winter softens the ground. If you need it done by a date, say so on the visit.

The visit itself is usually within a few days of you asking, and the quote is free with no obligation. Recent finished jobs are on our work page, and what moves the price is on the cost guide.

Questions people ask about this.

How long does a two-car block paving driveway take?

Two to three days on site for most Milton Keynes houses. Day one is dig out and base, day two is laying, and a third day if there is a lot of cutting, steps or a wall. You can usually park on it the day after we finish.

How long does a resin driveway take?

Two days on site if the base is sound, then usually about 48 hours before you drive on it. If the old surface has to come out and a new base go in, add a day.

Does rain stop the job?

Heavy rain can stop resin being laid, because it needs a dry surface to bond. Block paving and tarmac carry on in most weather. If a day is lost to weather Terry tells you that morning and the day count moves by one, not the price.

Do I need to be home while you work?

No. We need access to the front, water and power on the first day. Terry updates you by text or WhatsApp, and you can park on the road while the drive is out of action.

How long does a patio take?

A flat garden with a simple patio is 2 to 4 days. Levelling and steps is 3 to 5 days, up to a week with a retaining wall. Terry gives you the day count with the quote.

Terry O'Reilly

Written by Terry O'Reilly

Owner of Unique Driveways MK Ltd. 17 years on the tools, 299 public reviews on five platforms, and 5.0 on Google. He quotes every job himself.

Free site visit

Talk to Terry about your job.

Call Terry or WhatsApp a photo of the space. Or answer four quick questions below and send them to Terry by email.

  • Free, on site, no obligation
  • One written price, agreed before we start
  • Terry replies the same day, Monday to Saturday
  • 14-day cooling off

Step 1 of 4

What do you need?